A four-week QA pilot produces a decision when three things are fixed before day one: the question the pilot answers, the pass criteria for each week's deliverable and the date of the decision meeting. Week one delivers access and a test plan, week two a first test cycle with defect reports, week three automation running in the buyer's pipeline, and week four a regression run, a test summary report and a handover pack. Each week passes or fails on criteria the buyer wrote in advance.
On this page
What the pilot has to decide
A pilot answers one question: whether the proposed team can test the buyer's product to the standard the proposal described, on the buyer's tools, inside the buyer's working week. It is not a discovery phase and not a free sample. A pilot that tries to answer "is this vendor good" produces an impression; a pilot that answers "did this team meet these written criteria on this component" produces a decision.
The component should be small enough to cover in four weeks and real enough to carry risk. A payment flow, an onboarding screen set or one service with its API (application programming interface, the layer other services call) fits. A whole product does not, because the vendor then chooses which parts to test, and the buyer learns about the vendor's choices instead of its testing.
Four weeks is a design choice, set against what vendors publish about their own start-up time. One ranked vendor's case study reports that its functional QA team took two weeks to be fully operational after joining a game project ev-testronic-case-001confidence B. That is one published account, not a norm, but on that account a two-week pilot would end about when the team became fully operational. A four-week pilot leaves weeks three and four for the buyer to see the team after that point.
The pilot charter is a one-page document that states the component, the decision question, the pass criteria per week, the names of the buyer's triage (the review that decides whether each reported defect is valid, a duplicate or a rejection, and how severe it is) owner and decision makers, and the date of the decision meeting. The vendor signs it with the contract. The RFP template and scoring sheet supplies the sheet in which the buyer records the pilot evidence afterwards.
Before day one: contract, data, code and calendar
The paperwork decides whether the pilot can run on real conditions, so it is finished before the first login. Four items belong in it.
The first is the data processing contract. Where pilot testers touch personal data, the processing must be governed by a contract that sets out the obligations of the processor (the party that handles personal data on behalf of the organization that decides why and how it is processed) listed in GDPR (General Data Protection Regulation, the EU data protection law) Article 28(3) ev-market-reg-007confidence A. Data protection by default requires that only the personal data necessary for each purpose is processed ev-market-reg-005confidence A. Personal data that went through pseudonymization (replacing names and other direct identifiers with codes, with the key kept separately) and can be linked back to a person with additional information still counts as information on an identifiable person ev-market-reg-002confidence A. The simplest pilot runs on synthetic test data, and the charter says so.
The second is ownership of the test code written in week three. Under the Polish Copyright Act, an agreement transferring an author's economic rights requires written form, on pain of nullity ev-content-contracts-005confidence A. Where Polish law governs the pilot contract, a pilot agreed in an email exchange can leave the week-three automation without a valid transfer, so the pilot contract carries the same rights clause as the main contract. The contracts guide covers the clause wording.
The third is the team. The charter names each pilot tester with city and contract type, and those names should match the proposal. A pilot staffed by a presales group that will not join the engagement tests the wrong people.
The fourth is the calendar. Poland's public holidays in 2026 include 24 and 25 December, a Thursday and a Friday ev-market-tz-046confidence B. A pilot that starts on Monday 30 November 2026 loses both days in its fourth week, which is the week of the regression run and the handover. A US buyer that observes the federal holiday also loses Thanksgiving on Thursday 26 November 2026 ev-content-usschedule-003confidence A, so a pilot starting on Monday 23 November runs its access week with the buyer's side out for at least one day. Count working days on both sides before fixing the start date.
The four weeks, deliverable by deliverable
Each week ends with a deliverable and a short review against the charter. A failed week does not stop the pilot; it is recorded with its reason and carried to the decision meeting.
- Week 1: access, product walkthrough and a written test plan
Deliverables: access confirmed on the buyer's checklist (tracker, repository, test environment, chat); a test plan for the pilot component naming scope, out-of-scope areas, risks, test types and the exit criteria (the conditions that must hold before a test activity counts as finished) the vendor proposes; a list of open questions for the product owner.
Pass criteria: the buyer's QA lead accepts the plan without rewriting its scope; every tester on the team is the person named in the charter, in the city named; no request for production personal data arrives outside the data processing contract; the open questions are about product behavior, not about access the buyer already granted.
- Week 2: first full test cycle on the pilot component
Deliverables: executed test cases recorded in the buyer's tool; defect reports filed in the buyer's tracker, not in a vendor spreadsheet; a requirements-to-tests coverage map; two written status notes.
Pass criteria: the buyer's developers can reproduce each sampled defect report from its steps alone; the rejected-report count stays under the limit written in the charter, with a reason recorded for each rejection; the vendor finds defects from the hidden defect list (see below) at or above the charter's threshold; at least one report concerns a defect the buyer did not already know about.
- Week 3: automation running in the buyer's pipeline
Deliverables: automated checks for an agreed smoke test (a short set of checks that the main functions work at all, run before deeper testing) or regression subset, committed to the buyer's repository from the first commit; the suite wired into the buyer's CI (continuous integration, the pipeline that builds and tests code on each change) on each merge or nightly; a setup guide; a log of every failing run with its classification.
Pass criteria: an engineer from the buyer's team runs the suite locally from the setup guide without vendor help; a failure reaches developers through the buyer's normal channel; every failure in the log is classified as product defect, test defect or environment problem; no test is disabled without a logged reason.
- Week 4: regression run, summary report, handover and deletion
Deliverables: a regression run on a release candidate (a build the team intends to ship unless testing finds a blocking defect) of the pilot component; a test summary report covering what was tested, what was not and why, defects by severity and open risks; a handover pack (test cases, automation, environment notes, open defects); written confirmation that any personal data used was deleted or returned; the vendor's proposed steady-state team.
Pass criteria: the report names its untested areas and gives a reason for each; the buyer's QA lead could continue testing from the handover pack alone; deletion is confirmed in writing, which matches the GDPR rule that the processor contract provides for deletion or return of personal data after the services end ev-market-reg-013confidence A; the steady-state team names match the pilot team, or each change is stated with its reason.
Scoring the pilot against the buyer's own baseline
Each pass criterion compares the vendor with a number the buyer already holds, so the baseline is taken before the pilot starts. Defect reproduction, rejected reports and regression time all need a figure from the buyer's own team on the same component. The post on running a QA audit before outsourcing covers how to collect that baseline.
The hidden defect list is the buyer's control sample. Before day one, the buyer's QA lead writes down known defects in the pilot component that are still open or were fixed in an earlier release that the pilot environment still runs. The list stays with the buyer. At the end of week two, the triage owner counts how many the vendor reported unprompted. The count measures search depth on the buyer's product, which a case study cannot.
One person on the buyer's side triages every pilot report, and the same person does it for both vendors when two are piloted together. Triage decides duplicates, rejections and severity, so two triage owners produce two scales.
Pilot evidence goes into the buyer's own scoring sheet, whose rows mirror the dimensions in this site's methodology; the ranking itself does not score pilots. The week one test plan goes into the sheet's QA depth row. Week three goes into the automation row, the dimension the test automation page compares across vendors from published evidence. The data handling in week one and the deletion in week four go into the compliance row. The team-name checks go into a team location note in the sheet, and the status notes go into the nearshore fit row.
Three outcomes and what each one triggers
The charter lists the permitted outcomes before the pilot starts: award, extend with a named gap, stop. Writing them down in advance stops the meeting drifting into "one more month to see".
Award: every week passed, or a failed criterion was fixed within the pilot with a recorded cause. The main contract starts with the pilot team, and the pilot's test plan, automation and handover pack become the engagement's starting assets.
Extend with a named gap: one criterion failed, and the vendor has proposed a specific fix. The extension names the single criterion, the fix and a date for one re-check. An extension that does not name the criterion is a second pilot without a charter.
Stop: two or more weeks failed, or the team named in the charter did not do the work. The buyer pays the pilot invoice, keeps the code and the reports, and moves to the next vendor on the scoring sheet. Reference calls belong before this meeting rather than after it; the post on reference calls with a QA vendor's clients lists the questions that test what a pilot cannot, such as how the same team behaved in its second year. A buyer who already judged the vendor's published cases can compare them with the pilot result using the case study rubric.